Vertical Cylindrical Cryogenic Ethylene Storage Tank Flat Bottom Double Walled Tank

Basic Information
Place of Origin: China
Brand Name: CNASEC
Certification: API,AMSE,ISO9001, GB
Model Number: 20000m3
Minimum Order Quantity: >1
Name: Cryogenic Ethylene Tank Type: Vertical Cylindrical Flat Bottom Double - Walled Tank
Capacity: 20000m3 Effective Volume (m3): 20000(-165℃)
High Light:

liquid nitrogen cryogenic tank

,

cryogenic liquid storage tank

Vertical Cylindrical Cryogenic Ethylene Storage Tank Flat Bottom Double Walled Tank
Reference Project
In January 2013, we undertook the 20,000m3 cryogenic Ethylene storage project (2nd phase) for Nanjing Longxiang Liquid Chemical Storage company. It's the second time cooperation with Nanjing Longxiang after safety and stable running of the first project since 2007.
Technical Parameters
Equipment name 20000m3 cryogenic Ethylene storage tank 20000m3
Type Vertical cylindrical flat bottom double - walled tank
Design data Inner tank Outer tank
Design pressure (kPa) -- -0.5/25
Design temperature(℃) -105 (-20~+50)
Working temperature(℃) -102 Normal Temperature
Inner tank medium Cryogenic Ethylene

Expansion perlite+BOG

 

Effective volume (m3) 20000(-165℃) -
Design liquid level(mm) 25000 -
Corrosion allowance(mm) 0 1
Diameter D(mm) 33000 35000
Height(mm) 26100 27530
Main material 06Cr19Ni10 Q345R
Daily evaporation rate(%) ≤0.08

Our Strength

With over 30 years of laborious development, CNASEC has become a national engineering company taking technology as the core while developing engineering design, consultation and EPC projects simultaneously. We adheres to the policy of creating value for customers and take quality as priority. Keep on providing service to the customers at domestic and abroad as always. We will also make unremitting efforts to become an international engineering company with obvious characteristics and strong design, procurement, project management and general contract ability.

Vertical Cylindrical Cryogenic Ethylene Storage Tank Flat Bottom Double Walled Tank 0

To date, CNASEC has established over 30 projects related to LNG and Ethylene etc., and been equipped with the ability of designing and developing 100,000m3-level full containment tanks. In addition, the company has successfully generalized a set of standardized systems of storage tank engineering, realizing the short-term goals of the construction period and successfully shaping the national brand image of large-scale cryogenic liquefied storage and transportation projects!

Vertical Cylindrical Cryogenic Ethylene Storage Tank Flat Bottom Double Walled Tank 1

Advanced Design Software

◆Engineering Drawing Software:AUTOCAD

◆ 3D Factory Model Real-time Roaming:NAVISWORKS

◆Process Simulation Software:HYSYS

◆Pipeline Stress Analysis: CESAR II

◆Structural Analysis: ANSYS, ABAQUS, LUSAS,STAAD

◆3D Piping Arrangement System:PDMS

◆Project Management Software: PROJECT

http://mao.ecer.com/photo/cryogenic-engineering/editor/20190505171659_77126.jpg

Strict Site Construction Management

Vertical Cylindrical Cryogenic Ethylene Storage Tank Flat Bottom Double Walled Tank 3

Outer Tank Bottom Plate Assembly, Welding and Inspection

Assembly of main beam, ring beam

Vertical Cylindrical Cryogenic Ethylene Storage Tank Flat Bottom Double Walled Tank 4

Inner tank ceiling plate, hanger rod and vault assembly

Vertical Cylindrical Cryogenic Ethylene Storage Tank Flat Bottom Double Walled Tank 5

Outer tank plate installation

Vertical Cylindrical Cryogenic Ethylene Storage Tank Flat Bottom Double Walled Tank 6

Installation of top platform and outer tank ladder

Typical Reference List

 

No. PROJECT NAME OWNER PROJECT LOCATION TASK UNDERTAKEN PERIOD REMARK
1 Shanxi Fenghe 29,000 m3 LNG Full-containment storage tank project Shaanxi Fenghe New Energy Development Co., Ltd. Shanxi Province, China 29000m3 LNG full capacity storage tank 2019 Under construction
2 20,000m3 LNG bimetal full containment storage tank of Yubei LNG Peak-shaving Station Natural Gas Storage and Transportation Co., Ltd. , Jiaozuo City Henan Province, China 20000m3 bimetal full tank 2018 Under construction
3 20,000m3 LNG bimetal full capacity storage tank of Yudong LNG Peak-shaving Station Natural Gas Storage and Transportation Co., Ltd., Zhoukou City Henan Province, China 20000m3 bimetal full tank 2018 Under construction
4 20,000m3 LNG bimetal full containment storage tank of Yunan LNG Peak-shaving station Natural Gas Storage and Transportation Co., Ltd., Zhumadian City

Henan

Province,

China

20000m3 bimetal full tank 2018 Under construction
5 20,000m3 LNG bimetal full capacity storage tank of Yuzhong LNG Peak-shaving Station Natural Gas Storage and Transportation Co., Ltd., Zhengzhou City

Henan

Province,

China

20000m3 bimetal full tank 2018 Under construction
6 Langfang ENN Energy Co., Ltd. LNG Storage Station Project Langfang ENN Energy Co., Ltd.

Hebei

Province,

China

10000m3 bimetal full tank 2019 Under construction
7 China Coal Erdos Energy Chemical Co., Ltd. Synthetic gas system annual production capacity of 1 million tons of methanol technical renovation project China Coal Erdos Energy Chemical Co., Ltd.

Inner Mongolia Autonomous Region,

China

10000m3 bimetal single tank 2019 Under construction
8 Lianyungang Rongtai cryogenic ethylene, ammonia storage tank and auxiliary facilities project Lianyungang Rongtai Chemical Storage Co., Ltd.

Jiangsu Province,

China

The EPC project including one 20,000 m3 cryogenic Ethylene storage tank.

one 50,000 m3cryogenic Ammonia storage tank.

Ten pressure ball tanks and its auxiliary system such as storage and transportation process system, utility engineering system etc.

 

2018 Under construction
9 Jiaxing Yipeng Chemical Fiber LNG Station Project Jiaxing Yipeng Chemical Fiber Co., Ltd.

Zhejiang Province,

China

LNG gasification station EPC 2018 Under construction
10 Baoding Xinao Gas Co., Ltd. LNG Emergency Reserve Station Baoding Xinao Gas Co., Ltd. Hebei Province, China 20000m3 bimetal full containment storage tank 2018 Completed
11 Malaysia Refining & Petrochemical Comprehensive Development Project PETRONAS MALAYSIA Malaysia 20000m3 bimetal full containment storage tank 2017 Under construction
12 Hengli Petrochemical 20 million tons / year refining and chemical integration project Hengli Petrochemical (Dalian) Refining & Chemical Co., Ltd. Liaoning Province, China Low temperature ethylene liquid storage tank and liquid supply system 2017 Under construction
13

 

Yantai Muping District Qinshui Han Industrial Park Supporting LNG Gas Station

Yantai Haishun New Energy Co. Ltd..

Shandong

Province, China

LNG Gas Station EPC 2017 Completed
14 China Shipbuilding Heavy Industry(Handan) Pairui Special Gas Co. Ltd.. Annual production of 5,400 tons of new materials project China Shipbuilding Heavy Industry(Handan) Pairui Special Gas Co., Ltd..

Hebei

Province, China

 

1000m3 Liquid nitrogen tank

2017 Completed
15 100×104/year light hydrocarbon integrated utilization project Shandong Yuhuang Chemical (Group) Co., Ltd. Shandong Province, China

General contracting on storage tank.

Incl. design and fabrication of 2×10000m3 Ethylene Storage Tank

2017.07~

2018.05

Under construction
16 Natural gas reserve & peak-shaving project Xin’di Energy Engineering & Technology Co., Ltd. Hebei province, China

General contracting on storage tank.

Incl. design and fabrication of 2×10000m3 LNG full containment storage tank

2016.12~

2017.08

Under construction
17 110×104Nm3/d Natural gas liquefaction factory project Pesi Energy Co., Ltd. Inner Mongolia, China

General contracting on storage tank.

Incl. design and fabrication of 20000m3 LNG storage tank

2016.07~

2017.09

Under construction
18 4×500,000Nm3/d Natural Gas Liquefaction Project(LNG) Inner Mongolia West Region Natural Gas Co., Ltd. Inner Mongolia, china

General contracting on storage tank.

Incl. design and fabrication of 2×10000m3 LNG storage tank

2014.09~

2015.05

Completed
19 Comprehensive utilization of clean fuels with capacity of 100×104Nm3/d(LNG) Sichuan Guangneng Energy Co., Ltd.

Sichuan,

China

General contracting on storage

Tank.

Incl. design and fabrication of 20000m3 LNG storage tank

2014.02~

2015.04

Completed
20 Coalbed Gas Liquefaction Project Shanxi Jinxibei Natural Gas LLC

Shanxi,

China

EPC PROJECT

Incl. 5000m3 LNG storage

Tank design and fabrication.

2014.02~

2014.11

Completed
21

20000m3 Cryogenic Ethylene Storage Tank

(The second phase)

Nanjing Longxiang liquid chemical storage terminal Co. Ltd.

Nanjing,

China

EPC PROJECT

Incl. design and fabrication of 20000m3 Cryogenic ethylene storage tank.

2013.02~

2014.05

Completed
22 500×104Nm3/d LNG Plant Kunlun Energy Co., Ltd.

Hubei,

China

Design engineering,

Design for 2×30000m3 LNG storage tank

2012.06~

2013.05

Completed
23 CNPC LNG Reserve Project Kunlun Energy Co., Ltd.

Hainan,

China

General contracting on storage tank.

Incl. design and fabrication of 2×20000m3 LNG Storage Tank

2012.03~

2014.03

Completed
24 30×104Nm3/d Natural Gas Liquefaction, Storage & peak-shaving base Shandong Xi’neng Natural Gas Utilization Co., Ltd

Shandong,

China

EPC PROJECT

Incl. 5000m3 LNG storage

Tank design and fabrication.

2011.06~

2013.05

Completed
25 Large-scale clean fuels project for natural gas vehicle Sichuan Tongkai Energy Technology Development Co., Ltd.

Sichuan,

China

General contracting on storage tank.

Incl. design and fabrication of 30000m3 LNG Storage Tank

2011.06~

2013.12

Under construction
26 Natural Gas Liquefaction Project Baotou Huanda New Energy LLC

Inner Mongolia,

China

General contracting on storage tank.

Incl. design and fabrication of 10000m3 LNG Storage Tank

2011.01~

2012.06

Completed
27 1.2×108Nm3/Y Synthetic Natural Gas Project Inner Mongolia Xinkuang Energy Co., Ltd.

Inner Mongolia,

China

General contracting on storage tank.

Incl. design and fabrication of 5000m3 LNG Storage Tank

2010.11~

2012.06

Completed
28 Natural Gas Liquefaction Project Baotou New Energy Development LLC

Inner Mongolia,

China

General contracting on storage tank.

Incl. design and fabrication of 10000m3 LNG Storage Tank

2010.07~

2011.11

Completed
29 Natural Gas Utilization Project Xin’ao Fuel Gas

Hunan

China

General contracting on storage tank.

Incl. design and fabrication of 20000m3 LNG storage tank

2009.07~

2012.02

Completed
30

20000m3 Cryogenic Ethylene Storage Tank

(The first phase)

Nanjing Longxiang liquid chemical storage terminal Co. Ltd.

Nanjing,

China

EPC PROJECT

Incl. design and fabrication of 20000m3 Cryogenic ethylene storage tank.

2006.12~

2007.07

Completed